Ramblewood Gatehouse Refurbishment

  • Champion: Nebrich
  • Status: Completed
  • Entity: CWCDD
  • Description
    • Develop scope and SOW for RW gatehouse substantial refurbishment on existing footprint in lieu of RW Gatehouse expansion project. Includes: complete interior restoration, complete exterior restoration, new windows and doors. Operate within the contract originally signed in July 2020. Recapture as much value from the deposit money
  • Notes:
    • Delays caused from termination of contractor hired by in July 2020. With assistance from District Engineer, onboarded alternate general contractor to complete scope and allow for reopening of the gate.
    • Terminated Grace Construction in May 2024
    • Commenced work on remaining scope in July 2024
    • The Ramblewood gatehouse has been completely refurbished including the low-voltage system that supports the access control gates.